Durable Link Slab for Jointless Bridge Decks
Based on Strain-Hardening Cementitious Composites
Construction Timeline
In cooperation with the Michigan Department of Transportation (MDOT), HNTB Engineering Consultants, Midwest Bridge Contractors, and Clawson Concrete Company, construction of a demonstration ECC link slab began in July, 2005. The southeastern Michigan project site is Grove Street over Interstate 94 (S02 of 81063) in Ypsilanti, approximatly 45 minutes outside of Detroit, Michigan. The bridge was reconstructed in two halves, with Phase 1 completed in late September. Through the cooperation of state transportation officials, industry consulting engineers and contractors, and ACE-MRL research personnel, this first infrastructure demonstration project of ECC material in the US was completed on October 30, 2005.
|
Date |
Activity
|
Photos
|
|
October 30 - Phase 2
|
Opened Grove Street bridge to traffic
|
Open traffic
/iDSCN4049.jpg)
ECC link slab in use
/iDSCN4055.jpg)
Completed Grove Street over I-94
|
Completed ECC link slab
/iDSCN4052.jpg)
Repaired pier under link slab
|
|
October 29 - Phase 2
|
Completing hot mix asphalt (HMA) approach sidewalks and general site cleanup
|
Spreading HMA
|
Completed HMA approach sidewalk
|
|
October 29 - Phase 2
|
Load testing
|
Loading individual spans
|
Loading both adjacent spans
|
|
October 16 - October 28
Phase 2
|
Formed and placed concrete sidewalk, concrete barrier wall, metal hand railings, and bridge approach slabs
|
Concrete sidewalk formwork
/iDSCN3971.jpg)
Concrete barrier formwork
/iDSCN3970.jpg)
Completed bridge end approach
|
Preparing for bridge end approach
/iDSCN3977.jpg)
Concrete barrier formwork
/iDSCN3999.jpg)
Assembling metal handrails
|
|
October 15 - Phase 2
|
Pouring of ECC Link Slab
|
Material testing and certification
/iDSCN3904.jpg)
Discharge of ECC from truck
/iDSCN3930.jpg)
Screeding ECC surface
/iDSCN3941.jpg)
Tyning driving surface
/iDSCN3962.jpg)
Cast ECC link slab
|
Delivery of ECC Material
/iDSCN3926.jpg)
Flowable ECC Material
/iDSCN3939.jpg)
Steel troweling ECC surface
/iDSCN3951.jpg)
Tyned ECC/Concrete Interface
/iDIMG_0754.jpg)
Applying curing compound
|
|
September 23 – October 14
Phase 2
|
Completed demolition, stay-in-place formwork, installation of concrete deck reinforcing steel bars, and preparation of link slab formwork.
|
Conventional expansion joint
/iDSCN3886.jpg)
Placing reinforcing steel
/iDSCN3888.jpg)
Link slab transition zone
|
Stay-in-place formwork
/iDSCN3884.jpg)
Link slab location with rebar
/iDSCN3885.jpg)
Nearly complete reinforcing steel
|
|
September 23 - Phase 1
|
Opened new portion of Grove Street bridge to traffic and closed remaining old portion for rehabilitation
|
Completed ECC Link Slab
|
Completed ECC Link Slab
|
|
September 19 - Phase 1
|
Load testing
|
Loading individual spans
/iDSCN3806.jpg)
Wireless data collection
|
Side by side loading
/iDSCN3810.jpg)
ACE-MRL Researchers
|
|
September 13 - September 20, Phase 1
|
Formed and placed concrete sidewalk, concrete barrier wall, metal hand railings, and bridge approach slabs
|
Sidewalk forming
/iDSCN3836.jpg)
Concrete barrier wall forming
|
Sidewalk reinforcing bars
|
|
September10
Phase 1 |
Pouring of ECC link slab.
|
/linkslabpour1.jpg)
Prepared Link Slab
/linkslabpour3.jpg)
Placement of ECC
/linkslabpour5.jpg)
Placement of ECC
/linkslabpour7.jpg)
Screeding of Link Slab
|
/linkslabpour2.jpg)
Arrival of Concrete Trucks
/linkslabpour4.jpg)
Placement of ECC
/linkslabpour6.jpg)
Self-Consolidating ECC
/linkslabpour8.jpg)
Finished Link Slab
|
|
August 25 - September 6
Phase 1
|
Completed stay-in-place formwork, installation of concrete deck reinforcing steel bars, and preparation of link slab formwork.
|
Completed Formwork
/rebar2.jpg)
Installation of Rebar
/rebar3.jpg)
Completion of Rebar
|
Installation of Rebar
/linkslablocation2.jpg)
Link Slab Preparation
/linkslablocation3.jpg)
Link Slab Preparation
|
|
August 4 - August 25
Phase 1
|
Cleaning of steel girders, removal of old shear connectors, installation of stay-in-place formwork, and installation of new shear connectors.
|
Cleaned Girders
/girderprep2.jpg)
Girder Preparation
/newshear.jpg)
New Shear Connectors
|
Link Slab Location
/stayinplaceforms.jpg)
Stay-in-Place Formwork
/blasting.jpg)
Sandblasting Girders
|
|
August 2
Phase 1
|
Completion of concrete deck demolition and preparation of exisiting steel girders.
|
Completion of Demolition
/democomplete3.jpg)
Removal of Shear Studs
|
Completion of Demolition
/democomplete5.jpg)
Steel Girders
|
|
July 28 - August 1
Phase 1
|
Night demolition of concrete bridge deck. |
/nightdemo1.jpg)
Night Demolition
|
/nightdemo2.jpg)
Night Demolition
|
|
July 26
Phase 1
|
Removal of temporary bituminous asphalt riding surface on bridge deck. |
/bitremoval1.jpg)
Removal of Asphalt Surface
|
/bitremoval2.jpg)
Removal of Asphalt Surface
|
|
July 23
|
ECC trial mixing at Clawson Concrete. |
Concrete Truck Mixing
/trialmix3.jpg)
Discharging ECC from Truck
|
Self-Consolidating ECC
/trialmix4.jpg)
Screeding of ECC
|
|
July 5
|
Grove Street bridge before any construction activity.
|
Grove Street Before
/grovefar.jpg)
Grove Street Over I-94
|
Joints Before Link Slab
/refclose.jpg)
Bridge Pier Under Link Slab
|
|